Click on any of the available links below to view the progress of Bonnell's new 5500-Ton Press
Roof (Mar 23 - Apr 3)
Sidewalls (Apr 23 - May 14)
Press Foundation I (May 14 - May 29)
Press Foundation II (Jun 1 - Jun 12)
Press Foundation III (Jun 15 - Jul 2)
Press Flooring (Jul 6 - Jul 28)
Age Oven Foundation (Jul 28 - Aug 12)
Age Oven Install I (Aug 13 - Aug 28)
Age Oven Install II (Aug 31 - Sep 12)
Age Oven Install III (Sep 14 - Sep 22)
Handling System Foundation I (Sep 23 - Oct 5)
Handling System Foundation II (Oct 6 - Oct 19)
Handling System Install I (Oct 20 - Oct 30)
Handling System Install II (Nov 23 - Dec 8)
Press Install I (Oct 30 - Nov 9)
Press Install II (Nov 10 - Nov 24)
Press Install III (Nov 25 - Dec 7)
Full Sequence (Mar 23 - Dec 7)
Abrev. Full Sequence (Mar 23 - Dec 7)
Extrusion
Capabilities
Alloys
Finishes
Billets
Extrusion Process
Standard Shapes
New 5500 Ton Press
New Acid Etch Anodizing
Press Progress
Open Shapes
Live Chat
© 2008 - 2010 Bonnell Aluminum | Contact Us | Legal Notice/Privacy Policy | Site Map | Client Log-in